CINA Haiti: Benvenuto

CINA Energy System

Integration of renewable energy in the microgrid of the National Cement Plant  and of the local community of villages of Source Matlas

Location

Port au Prince, Haiti

Period

Sept 2017- May 2018

Client

Cementos Argos
CINA Foundation

Areas of focus

Integration of Renewables
Solar PV

CINA Haiti: Elenco
IMG_20180302_124707.jpg

Optimisation of renewable energy assets

The Team has performed a complete study of the energy system of the National Cement Plant of Haiti CINA, identifying demand patterns, reliability requirements and performing a bottom-up study of the O&M costs, consequence of the deterioration of the plant.

Using commercially available modelling tools, the team has succesfully assessed the optimal techno-economic integration of renewable energy assets (mainly photovoltaic arrays, wind turbines and batteries) to retrofit the operational costs and reduce the final LCOE

Local community inclusion

A study of the local community of Source Matelas has been performed in cooperation with CINA Foundation, with the goal to identify consumption patterns of the urban areas nearby the cement plant.


The electricity demand of the community has then been integrated in the analysis of the energy system of the cement plant, and in the optimization of the required energy assets

27419534698_0f9791c394_o.jpg
IMG_20180302_121925_edited.jpg

Definition of the strategic business goals

In cooperation with the management of the cement plant, several business cases and different logistic scenarios have been investigated.

The local constraints in terms of supply chain and legal restrictions have been taken into account to improve the study to a perfect match between optimal economic, reduction of the emissions and comfort of the client